Some updates regarding the #DC_AC_Conversion of Thane-CSTM Section:
Thane-CSTM has been included in the list of quickly achievable projects (during next 100 days) asked by Hon’ble MR.
Target - 30.08.2014 (Deadline imposed through PMO/RM)
.
....
more...
.
1. Lowering of tracks( 10mm to 90 mm) for balance 8 ROBs/FOBs to suit the running of rolling stock with maximum height of 4270 mm.
TDC- 06.08.2014.
.
2. Critical OHE activities i.e. laying of feeder( Aerial/Cable), removal of old redundant portal booms and erection of boom & TTB, modification of OHE under ROB/FOB are required to be completed by 15.08.2014.
.
3. PSI works including TSS and switching stations at Sion, Chinchpokli, Kanjur marg, Matunga, Parel, Sandhurst Road and CSTM are being executed by MRVC .
TDC- 15.08.2014.
.
4. Conversion works related to S&T .
TDC- 31.07.2014.
.
5. Commissioning of AT, CLS , retention of 2.2 kV feeder-1 for Electrical General Services to be completed by 15.08.2014.
.
6. Condonation proposals for vertical infringement of FOBs/ROBs to be submitted to CRS by 31.07.2014. (The proposal are with COM.
Issue of restricting Rolling Stock upto a height of 4270 mm in TNACSTM, Excl. 5th & 6th line upto LTT, is under deliberation with CME & COM. Condonation papers will be signed by COM after finalisation of this issue.)
.
7. Harbour and Transharbour lines also to be completed in the current financial year...