Bidar Gulbarga Line updates
--Almost tracks from Gulbarga station till Kamalapur is layed with some gaps in between for ROB/RUB and minor bridges...
--- Bennethora Bridge near Kurikota is completed only tracks needs to be layed
--- By this month end Engine will roll from Gulbarga station till kilometer 21 which will pass Bennethora bridge also and reach mahagoan
---...
more... Massive goods shed under progress at sultanpur station
-- Tracks from Kinni sadak till humanabad is also almost done except in few stretches...
-- Major bottleneck is Margutti tunnel it will take lot of time still