Ajmer ko palanpur #doubling update 357km
Incomplete in detail
Ajmer to durai gound levelling going on
Durai to magaliyawas almost complete 90%
Bangurgram halt to bewar 60% work done
Bewar...
more... to haripura 15% only done its takes min one year briges work going on
Aur doubling hu rehe h waha waha 80%
#electfication hu gaya h haripura to marwar outer 100% hu gaya h
On progress
1. Ajmer to magaliyawas 26km
2. Bangurgram halt to haripur 38km
3. Maval to bhimana 27 km
4. Kajoda to jatni 10 km
Appox in progress 100km
Complete
1. Palanpur to kajoda 7 km
2. Jatni to maval 27km
3. Bhimana to haripur 203km
4. Bangurgram to magaliyawas 27km
Complete appox 257 km