RE Update of LPJL-NZB (Lingampet-Jagityal --- Nizambad)
70% Wiring is done at Koratla Station same at Metpally but at Koratla in siding mast erection is left
1) Koratla stn outer
2) Koratla stn building...
more... 3) Towards Peddapalli (PDPL)
4) Towards Nizambad (NZB)
5) Basic facility - water Troughs are being constructed...
Between Metpally and Morthad Wiring is left, Between Morthad and Armoor minor foundations are left, on Armoor PFs Foundation is done, which is 30 kms far from NZB
Still SPs, SSPs are not constructed
The electrification of whole stretch of Peddapalli - Nizambad Railway Line completes in March
The CRS is expected in March - starting of April