#CRInfraUpdates
🟩Construction of 2 new Platforms for mail express at Lokmanya Tilak Terminus (LTT) of 10 meter width and of 24 coach length of 680 meters.
Mumbai...
more... division.
🪙Cost- 64.10 Crores
🪙Expenditure till date- 34.62 Crs
➡️Overall Physical Progress- 35%
🟩Scope of work -
➡️Construction of Pit Lines with pile foundation
➡️Construction of 2 Overhead Water Tank of 2.25 lakh litre capacity each
➡️Construction of Under Ground Water Tank of 4.5 lakh litre capacity
➡️Contruction of 4 Stabling Sidings
➡️Construction of 2 new Platforms for the Mail Express
➡️Dismantling of existing old tracks
➡️Construction of Wide Island Platform with Track
➡️Dismantling & Reconstruction of electric and mechanical office and store building
➡️Provision of Asphalt Roads of 7000 sq. mtr
➡️Provision of aprons for platforms
➡️Provision of shunting neck
➡️Slewing of track
➡️Extention of 2 FOBs from existing platform no. 4/5 to new platform no. 6/7
🟩Completed Works-
✅Construction of Pitline with Pile Foundation
✅Construction of 2 overhead water tanks (2.25 lakh ltrs)
✅Dismantling of 4 Stabling Sidings
✅Platform walling of 1060 meter out of 1200 meter completed
✅Dismantling of 4 Stabling lines is completed
✅1118 Mtr raft out of 1200 mtr washable apron of PF no. 6 & 7 completed
✅Under ground water tanks of 4.5 lakh ltr capacity
✅Asphalt road of 7000 sq. Mtr
🟧Works in Progress -
➡️Platform cover shed foundation work in progress
➡️Construction of wide island platforms with tracks
➡️Dismantling of existing old tracks
➡️Slewing of tracks
➡️Extention of PF No. 4/5 FOB to PF No. 6/7
Completion of these 2 new platforms will improve train mobility at LTT and will reduce the congestion.