Chennai Metro: Alstom Hands Over First Driverless Train Set For Phase II Project, To Be Tested On Poonamallee-Porur StretchChennai Metro Rail Ltd. (CMRL) has received its first driverless train for the Phase II expansion of its metro project. The train, manufactured by Alstom, is one of 36 ordered in February 2024 to operate on a 26-kilometer corridor connecting Poonamallee Bypass to Light House, covering 28 stations. The trains are...
more... part of a Rs 1,125.92 crore contract and were initially expected in August, but delays in procuring components pushed back the delivery. The train will first be tested on the Poonamallee-Porur stretch of Corridor 4, with full operations expected by late next year. Alstom previously supplied metro cars for Phase I of Chennai Metro's network in 2010.
Chennai Metro Rail Ltd. (CMRL) ne apne metro project ke Phase II expansion ke liye apna pehla driverless trainset receive kiya hai. Alstom, jo ki smart aur sustainable mobility solutions me mahir hai, ne yeh trainset banaya hai. Chennai Metro ne February 2024 me 36 driverless trains ka order diya tha,...
more... jismein har train mein teen car honge. Yeh trains 26 kilometer ke corridor par operate karenge, jo Poonamallee Bypass ko Light House se connect karta hai, aur ismein total 28 stations honge, jismein se 18 elevated aur 10 underground honge.