Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
News Super Search
 ↓ 
×
Member:
Posting Date From:
Posting Date To:
Category:
Zone:
Language:
IR Press Release:

Search
  Go  
dark modesite support
 
Tue Sep 17 21:08:31 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
RailCal Android App
RailCal iPhone App
Advanced Search
<<prev entry    next entry>>
News Entry# 565464
Aug 16 (19:45) Mumbai Metro 3 Line's First Phase to Be Operational by September 2023
Metro
MMOPL/Mumbai Metro
6250 views
1

News Entry# 565464   
  Past Edits
This is a new feature showing past edits to this News Post.
Metro 3’s Phase 1 to be launched by September; fully operational by next year

Mumbai's Metro 3 line, connecting Colaba, Bandra, and SEEPZ, is set to see its first phase between BKC and Aarey operational by September 2023. Delays in Phase 1 are attributed to pending MEP works, especially at airport stations. Phase 1 includes three packages (5, 6, and 7), with work ongoing at...
more...
Sahar, T1, and T2 stations. Construction at Sahar Road station is nearing completion, with escalator testing underway. T1 station, with significant commercial space, faced delays due to late entry and exit work, leading to deeper construction and temporary lobbies. A safety review will precede CMRS certification for commissioning. The second stretch from BKC to Cuffe Parade is anticipated to be operational between March and June 2024, with challenges at Girgaon and Kalbadevi stations. The original September 2023 deadline for the entire line was shifted to June, then August, and now September 2023 for Phase 1.

Mumbai ka Metro 3 line, Colaba, Bandra aur SEEPZ ko connect karta hai, ka first phase, BKC aur Aarey ke beech, September 2023 tak operational hone wala hai. Phase 1 mein delays MEP works ki wajah se aaye hai, especially airport stations pe. Phase 1 mein three packages (5, 6, aur...
more...
7) hai, jismein Sahar, T1, aur T2 stations pe kaam chal raha hai. Sahar Road station pe construction almost complete hai, aur escalator testing chal raha hai. T1 station, jismein significant commercial space hai, late entry and exit work ki wajah se delay hua, jiske wajah se construction deeper ho gaya aur temporary lobbies banaye gaye. Safety review CMRS certification se pehle hoga, Phase 1 ke commission hone ke liye. BKC se Cuffe Parade tak ka second stretch, March aur June 2024 ke beech operational hone wala hai, Girgaon aur Kalbadevi stations pe challenges ke saath. Original September 2023 deadline for the entire line ko pehle June, fir August, aur ab September 2023 tak Phase 1 ke liye shift kiya gaya hai.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy