Current status of PATAN-BHILDI gauge conversion !!
Registration Number : MORLY/E/2013/03771
Name Of Complainant : ARUN SINGH N
Date of Receipt : 06 May 2013
Received...
more... by : Ministry of Railways, ( Railway Board)
Forwarded to : CAO(C)
Contact Address : Churhgate Station Bldg. Ist floor
Mumbai
400020
Contact Number : 22076618
Grievance Description : sub- require details regarding the status of PATAN-BHILDI GAUGE CONVERSION (WESTERN RAILWAYS) respected sir , plese giv me all the information regarding the current status of patan-bhildi gauge conversion project wat is the distance between patan and bhildi ?? how much work is pending ?? when it will be completed ??? *****THANK YOU *****
Current Status : CASE CLOSED
Your Feedback :
Very Good
Date of Action : 29 Oct 2013
Details : Patan –Bhildi Gauge Conversion:- This work freezed by Rly.Board vide letter No. 89/W1/NL/W/19-pt.(1) dt. 29.04.1992 in view of Ahmedabad-Delhi Gauge conversion. The Railway Board vide letter No.94/W/1/GC/8/VG-MSH dated 01.03.2007, advised to take up the work. Detailed Estimate of Patan-Bhildi New BG Line costing 237.12 sanctioned by Railway Board on 27.01.2009. Possession of 144.70 hect.land out of 176.56 hect. has been completed. The work of formation making, minor bridges, major bridges is in progress where ever land is available. The NOC is awaited from National Monument Authority New Delhi for execution of work near “Rani KI Vav” monument.