Projects and their current status for Hisar Jn !
1> RE-HSR-JHL-LDH Electrification
i) Rewari-Manhru : Poles have been erected all over stretch while Rewari-Kosli stretch has been energized and commissioned
...
more... ii) Manheru-Hisar : Poles have been erected till Hisar yard and wiring has been done till mentioned location.TSS work is slowly moving
iii) Hisar-Jakhal : Poles have been erected on total stretch and TSS is about to complete as there has been a notice come out from RVNL to energize the section with 25KV
iv) Jakhal-Dhuri-Ludhiana : This section has been put on halt as division comes with its objection in front of RVNL as Division have not changed the signals from Semaphores to MACLS
2> Hisar-Bathinda-SOG Electrification
Foundations has been constructed till Sirsa and continuing with good pace and also poles are being erected.
3> Coach Care Complex,Hisar
This project will be completed in three phases where Phase one work for CCC is about to complete which includes civil and mechanical work for washing line and Sick line shed.
4> Lift and Escalator on PF 1 and 4
Lift structure i.e. Civil work has been completed where as lift work is moving in slow pace
5> New F.O.B from PF 1 to PF 6
Work has been alloted and yet to be start