Majority of hookes has been set up today, might be in another 2 days all Hookes of platform will be setup.3 more platform connecting poles to set.
2 key thing is yet to happen before completion of electrification of Bhagalpur:-
#Digging holes and fixing poles towards Kahalgaon side till the end of yard side crossing bolanathpul work is under progress
...
more... #Dismantling of low height FOB at mid of BhagalpurJn.
#Update:- Loco will be changed at BhagalpurJn for train passing through this route.
#Doubling- Linking of double line track till LMM is yet to be aligned at BhagalpurJn.Non interlocking under progress.
***Further LMM to ghogha 6km work also completed and trail has been conducted with light engine.CRS of LMM to Kahalgaon timeline was January 19. Hopefully not January but definitely by March CRS will happen.