Gooty- dharmavaram doubling: Travelled from gooty to anantapur today. Track has been laid from gooty cabin to turkhapalli.but electrification is pending.remaining portion turkhapalli to anantapur only land has been levelled. Sleepers and ballast has been procured. Between kalluru to garladinne in some places concrete beams has been laid and in some places pits are dig for laying concrete bases. Brides are almost in finishing stage and will be completed in next month.one bridge construction has to be started between garladinne and taticharla. New station building is under construction in garladinne/taticharla (forgot the station name) The total is expected to be completed by December 2020 or march 2021.