#JodhpurPhuleraElectrification
Work doing at decent speed.. Target 31 mar 2023.
Foundation complete between Kuchaman and Degana both up and down line.
Bahut sare pole Kuchaman per rakhe huye hain..
OHE erection work is 30%...
more... complete.
Some locations horizontal masts also placed.