Electrification progress on Moradabad - kashipur - Ramnagar route
Moradabad - Got outer :- Electrification is complete.
Got outer - Sehal Halt outer :- Foundation work complete, Poles erected, brackets not placed and wiring not done.
Sehal...
more... outer outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.
Kashipur :- Foundation work in progress and in some place poles also erected.
Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.
Ramnagar :- Foundation work complete, Poles erected but wiring not done.
This is the progress of electrification on Moradabad - Ramnagar route.
SSP details:-
Pipalsana SSP will complete finishing going on.
Roshanpur SSP will complete finishing going on.
Kashipur SSP work has not started.
Ramnagar SSP work has not started.
Note :-
Material for electrification has been dumped at Aliganj.