Sivok Rangpo New BG Rail Line Project Progress
(As on 31.12.22):
Overall Physical Progress: 51.45%
Completed...
more... Works:
- Tunnel Mining: 25.36 km
- Piling: 19537 m
- Piers: 442 m
- Earthwork: 4 Lcum
- Minor Bridge: 5
Source: Ministry of Railways Official Twitter Handle