- Nagpur 3rd/4th line -
ЁЯЯйCR has completed 147.77 km multitracking (new line/doubling/3rd/4thline) in current FY from April 2023 till date 2023.
ЁЯЯй3886.95 Crs planned by CR in this year for new lines/doubling/3rd/4th line/
ЁЯЯй2983.47 Crs expenditure till date
ЁЯЯйWardha - Nagpur 3rd/4th line -
тЮбя╕ПLength - 78.70 km
тЮбя╕ПLength commissioned - 34.59 km
тЮбя╕ПRemaining - 44.11 km
тЮбя╕ПOverall Physical Progress - (3rd line-72%) (4th line-70%)
ЁЯкЩ Cost - 1177.97 Cr
ЁЯкЩ Expenditure till date - 1035.92 Cr
A) Completed 3rd/4th line section
ЁЯЯйKhapri - Sindi - 34.59 km (43.95%)
B) Near Completion Section (27.14 kn (34.48%)
ЁЯЯйSindi - Seloo Road
ЁЯЯйKhapri - Ajni
C) In Progress Section 16.97 km (21.56)
ЁЯЯйSeloo Road - Wardha
ЁЯЯйAjni - Nagpur
тЮбя╕ПLand acquisition required - 38.858 Hectare
тЮбя╕ПLand acquisition completed - 38.818 Ha (99.50%)
тЮбя╕ПLand acquisition remained - 0.04 Ha
ЁЯЯйCompleted works details -
тЮбя╕ПEarthwork including blanketing - 21.40/32.63 Lcum(66%)
тЮбя╕ПImportant Bridges - 2/2 (100%)
тЮбя╕ПMajor Bridges - 10/12 (83%)
тЮбя╕ПMinor Bridges - 69/144 (48%)
тЮбя╕ПStation building - 2/7 ( 28%)
тЮбя╕ПTrack linking - 69/157 km (44%)
тЮбя╕ПOHE (Overhead equipment) Foundation- 1010/4048 (25%)
тЮбя╕ПOHE Mast erections - 890/3680 (24%)
тЮбя╕ПOHE Wiring Track km- 45/184 (25%)
тЮбя╕ПSignalling Electronic Interlocking - 6/20 Stations (30%)
тЮбя╕ПSignalling Indoor and Outdoor works - 6/20 (30%)
ЁЯЯйCompletion of Wardha - Nagpur section 3th/4th lines will help to increase train mobility and will reduce congestion of section on busy Mumbai Howrah Route.