#update5
Electrification progress on Moradabad - kashipur - Ramnagar route
Moradabad - Got outer :- Electrification is complete.
Got outer - Pipalsana outer :- Foundation work complete, Poles erected, brackets not placed and wiring not done.
Pipalsana...
more... outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.
Kashipur :- Foundation work in progress.
Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.
Ramnagar :- Foundation work complete, Poles placed but not erected.
This is the progress of electrification on Moradabad - Ramnagar route.
SSP details:-
Pipalsana SSP will complete in 7 days finishing going on.
Roshanpur SSP will complete in 7 days finishing going on.
Aliganj SSP will complete in 7 days finishing going on.
Kashipur SSP work has not started.
Ramnagar SSP work has not started.