Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
News Super Search
 ↓ 
×
Member:
Posting Date From:
Posting Date To:
Category:
Zone:
Language:
IR Press Release:

Search
  Go  
dark modesite support
 
Wed Sep 18 09:47:06 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
RailCal Android App
RailCal iPhone App
Advanced Search
<<prev entry    next entry>>
News Entry# 569305
Sep 13 (12:01) Construction of 5.1 km Bypass in Prayagraj to Ease Traffic Jams at Jasra Railway Crossing
Other News
NR/Northern
2184 views
0

News Entry# 569305   
  Past Edits
Sep 13 2024 (12:02)
Station Tag: Prayagraj Junction (Allahabad)/PRYJ removed by Adittyaa Sharma/1421836
Stations:  Jasra/JSR  
35 फीसदी हुआ काम, चार महीने में कैसे बनेगा जसरा बाईपास

A 5.1 km long bypass is being constructed to alleviate the daily traffic jams at the Jasra Railway Crossing in Prayagraj. Construction began on March 15th, with a target completion date of December 2024. The bypass will start from Pander village and end at Gauhania village, including a railway underbridge, a...
more...
large bridge near Amreha village, a small bridge over a drain near Dauna village, and another bridge over a canal near Khatangia village. A railway underbridge is also planned near Khatangia village. Despite the target completion date, only 35% of the construction is completed, with 400 workers working round the clock to meet the deadline.

Prayagraj mein Jasra Railway Crossing pe roz lagne wala jam se rahat dene ke liye 5.1 km lamba bypass banaya ja raha hai. Iska construction 15 March se shuru hua, aur December 2024 tak complete karne ka order diya gaya hai. Bypass Pander village se start hoga aur Gauhania village pe...
more...
khatam hoga. Isme ek railway underbridge, Amreha village ke paas ek bada bridge, Dauna village ke paas nala par ek chhota bridge, aur Khatangia village ke paas se guzarti naal par dusra bridge bhi banaya ja raha hai. Khatangia village ke paas hi ek railway underbridge banne ka plan hai. March se ab tak bypass ka sirf 35% work complete ho paya hai, lekin 400 workers din-raat kaam kar rahe hain.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy