Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
News Super Search
 ↓ 
×
Member:
Posting Date From:
Posting Date To:
Category:
Zone:
Language:
IR Press Release:

Search
  Go  
dark modesite support
 
Sun Sep 8 19:32:51 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
RailCal Android App
RailCal iPhone App
Advanced Search
<<prev entry    next entry>>
News Entry# 562536
Jul 29 (15:17) Andhra Pradesh Delays Nadikudi-Srikalahasti Railway Line Construction, Only Depositing Rs. 6 Crore (www.eenadu.net)
IR Affairs
SCR/South Central
7719 views
0

News Entry# 562536   
  Past Edits
Jul 29 2024 (15:17)
Station Tag: Nadikude Junction/NDKD added by Exynos9611~/2099623
Stations:  Nadikude Junction/NDKD  
read full article... నడికుడి-శ్రీకాళహస్తి.. పనుల్లో తీవ్ర జాప్యం

The Andhra Pradesh government has only deposited Rs. 6 crore for the construction of the Nadikudi-Srikalahasti railway line, despite it being a joint project with the central government where both parties were supposed to contribute 50% of the cost. The line was intended to connect a remote region and facilitate mineral...
more...
transportation, benefiting the local economy. However, the project has been delayed due to the state government's lack of participation in funding and slow land acquisition process. While the project was approved in 2011-12 with an estimated cost of Rs. 2,289 crore, it has been delayed since then, with only 45.5 km out of 309 km completed. The state government has reportedly contributed only a small fraction of its promised Rs. 780 crore, and the overall project cost has escalated to Rs. 3,122 crore due to delays.

Andhra Pradesh government, Nadikudi-Srikalahasti railway line ka construction ke liye, central government ke saath 50% cost share karne wala project mein, sirf Rs. 6 crore deposit kiya hai. Ye line ek remote region ko connect karega aur minerals ka transportation bhi karega, jisse local economy ko fayda hoga. Par, state government...
more...
ki funding mein kam interest aur land acquisition mein delay ki wajah se project mein delay aa raha hai. 2011-12 mein approve hua ye project, Rs. 2,289 crore ka estimated cost tha, lekin ab tak sirf 45.5 km complete hua hai, 309 km mein se. State government ne apna promised Rs. 780 crore mein se sirf ek chota sa hissa contribute kiya hai, aur delay ki wajah se overall project cost Rs. 3,122 crore tak badh gaya hai.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy