Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
News Super Search
 ↓ 
×
Member:
Posting Date From:
Posting Date To:
Category:
Zone:
Language:
IR Press Release:

Search
  Go  
dark modesite support
 
Sat Sep 14 05:20:29 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
RailCal Android App
RailCal iPhone App
Advanced Search
<<prev entry    next entry>>
News Entry# 566924
Aug 28 (11:12) Coal Transportation Project in BCCL Stalled Due to Ongoing Protests
Other News
ECR/East Central
4130 views
0

News Entry# 566924   
  Past Edits
Aug 28 2024 (11:12)
Station Tag: Sonardih/SZE added by AdittyaaSharma^~/1421836
Stations:  Sonardih/SZE  
महेशपुर में बने साइलो तक रेल लाइन बिछा रही राइट्स को 5वीं बार नहीं मिला समय विस्तार

The construction of a 3.5-kilometer railway line from Sonardih station to Maheshpur siding in Gobindpur area of ​​BCCL is facing delays due to local villagers' protests. The line, costing 82 crore rupees, is meant to transport coal from silos in Maheshpur to railway rakes. The work was awarded to Rites in...
more...
2014 and was supposed to be completed in 2019, but it remains unfinished in 2024. While the silo construction is complete, the lack of the railway line is hindering the coal loading process. The Board of Directors of BCCL has refused to grant a further extension to Rites, who have already received four extensions. Work has been halted since July 29th due to protests.

BCCL ke Gobindpur area mein Maheshpur ke silos tak coal pahunchane ke liye railway line bichha rahe Rites ko time extension nahi mila hai. Board of Directors ki meeting mein, Rites ne 15 August se 31 December 2024 tak time dene ka aagraha kiya tha, lekin board ne yeh request reject...
more...
kar di. Rites ko ab tak chaar baar time extension mil chuka hai. Chauthi baar diya gaya time extension 15 August ko khatam ho gaya. Yeh project 2014 mein start hua tha aur 2019 mein complete hona tha, par abhi bhi yeh project incomplete hai. Silos ka construction 5 saal pehle complete ho gaya tha, lekin railway line ka kaam abhi bhi pending hai. Silos se railway rakes mein coal loading ka kaam start nahi ho paya hai kyunki railway line complete nahi ho payi hai. 82 crore rupees ki lagat se 3.5 kilometer ki railway line bichhani hai, aur ismein se lagbhag 2 kilometer ka kaam complete ho chuka hai. Local villagers ki protests ki wajah se construction company ko 20 se zyada baar kaam rokna pada hai. 29 July se kaam band hai.
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy